这篇博客文章基于《 PMBOK指南》的第四版,以及第5版《 PMBOK指南》,PMI改变了此博客文章中manbet最新版使用的术语的定义;因此,这篇文章现在已经过时了。
我已经根据PMBOK指南的当前版本重新编写了此博客文章(6manbet最新版Th版)。请拜访:Work Performance Data and Work Performance Information。I am leaving this post in case someone wants to review the old post under the PMBOK Guide (4Th版)。
Management is always interested in the status and progress of the project. They want to know:
- 该项目的百分比已完成?
- 尚未完成什么百分比?
- 花了多少钱?
- What have you earned?
- Are you ahead or behind schedule?
So, how will you provide them with this information?
You can show them this information through the工作绩效报告。This report shows all the information required by项目利益相关者, as defined in the communication management plan.
要准备本报告,您将需要工作绩效信息和工作绩效测量。
工作绩效信息
Work performance information is the raw data of the project’s status. It refers to what percentage of work has been completed, how much time has elapsed, the cost incurred, and more.
It provides us with the current status of the项目。You use this information to create work performance measurements and then the work performance report.
工作绩效信息的一些示例如下:
- 多少工作已经完成?
- 时间表的进度是什么?
- 迄今为止已经发生了什么费用?
- 产品的质量指标是什么?
- 什么是风险状况?
- What is the采购表现?
工作绩效测量
Once you get the status, you compare it with your planned progress and come up with work performance measurements. They are the comparison between the planned progress and the current status of the project.
Some examples of work performance measurements include:
Schedule Performance
Here you will compare the planned schedule with the actual schedule.
For example, for an activity that was scheduled to be completed in five days, work performance measurements show how long it actually took to complete.
Cost Performance
在这里,您将将您计划的支出与实际费用进行比较。
For example, what was the planned cost for the activity, and how much did you actually spend to complete it?
质量性能
Here you compare the planned performance with the actual performance.
For example, you will measure how many defects, tolerance, and threshold were allowed and how many occurred.
风险性能
Here you will see the effectiveness of yourrisk management plan。
例如,您将看到发生了多少风险,与确定的风险以及风险响应计划的有效性等等。
采购性能
Here you will compare the seller’s actual performance against the planned performance.
The Difference Between Work Performance Information and Work Performance Measurements
工作绩效信息和工作绩效测量之间的差异如下:
- 工作绩效信息是可交付成果的“目前”状态,而工作绩效测量是实际状态和计划状态之间的比较。
- Work performance measurements are developed with the help of work performance information.
- Examples of work performance information include the time elapsed and money spent, while cost variance and schedule variance, cost performance index and schedule performance index, and more, are examples of work performance measurements.
Summary
Work performance information and work performance measurements help inearned value managementand forecasting. They help you prepare the performance report that you can send to your stakeholders. Based on this performance report, management decides how to proceed further.
希望您现在对工作绩效信息和工作绩效测量有更好的了解。
现在,您可以转到下一篇博客文章performance report。
嗨,法哈德,
请更新您的说明,如您所说,您将在PMBOK指南的第5版中更新博客,已删除工作性能测量,并添加了新的期限工作绩效日期。manbet最新版
Your expert guidance is very helpful to me.
Already updated.
这是更新的帖子:
//www.vhgallery.com/2013/10/work-performance-data-wpd-and-work-performance-information-wpi/
嗨,法哈德,
Thanks for the explanation. But, in the PMBOK- Fifth edition, they have Work Performance data, Work Performance Information and Work Performance Reports……it doesn’t have Work Performance Measurements…..even the output of the “direct and manage project work” process is “work performance data” in 5th edition and “work performance information” in 4th edition…..i’m getting really confused….please help
Hello Abhisek, I was about to update this blog to reflect the current status.
In the 5th version of the PMBOK Guide, Work Performance Measurement has been deleted and a new term Work Performance Date is added.
I am going to update this blog post very soon.
这是更新的博客文章的链接:
//www.vhgallery.com/2013/10/work-performance-data-wpd-and-work-performance-information-wpi/
清除了混乱。
Thanks Fahad Bhai
You’re welcome Saurabh.
在“简要摘要”中,第一个项目符号应该说WPM而不是WPI?
Thanks for the article!
Why? Any explanation?
Hi, i appreciate if you could explain the following
问:作为绩效测量的一部分,以下哪项未完成?
1.计算计划的价值
2.Calculating Earned Value
3.Calculating ETC
4.Calculating Cost Variance
他们说正确的答案是——计算Earned Value. Can you explain why is EV is not part of performance measurements?
谢谢!
Malika
I think because it is a part of Performance Report.
请参考以下职位 -
//www.vhgallery.com/2012/03/performance-report-in-project-management/
Let me know if you any other thoughts…
Would you say that WPM is simply the result of the variance analysis?
Variance Analysis is a Tool & Technique of Control Scope Process and Work Performance Measurement (WPM) is an output of this process.
In short, answer to your question is – Yes.
Thanks a lot
Thank you; I really appreciate your explanations.
欢迎您Deidra。
亲爱的
i ‘d like to exprees my apperciation about your help and attention
阿里·侯赛因(Ali Hussien)
谢谢。
在这里必须有点不同意。工作性能数据是原始数据。工作绩效信息是数据上下文化并将其列入可以以他们理解的方式向利益相关者报告的形式。
Yes, you're right and I'm agree with you. Where is the disagreement?
WPIis about gathering the information of the project and WPM is about analysing the information.
你是对的。