这篇文章是基于第四编辑ion of the PMBOK Guide, and from the 5th edition of the PMBOK Guide, the PMI has changed the definitions of terms used in this blog post; therefore, this post is now obsolete.
我根据PMBOK指南的版本重新编写了此博客文章。manbet最新版请拜访Work Performance Data and Work Performance Information。I am leaving this post in case someone wants to review the old post under the PMBOK Guide (4thedition).
管理人员始终对项目的状态和进度感兴趣。他们想知道:
- What percentage of the project is completed?
- What percentage is yet to be completed?
- How much money has been spent?
- 你赚了什么?
- 您是领先还是落后?
那么,您将如何为他们提供此信息?
您可以通过work performance report。This report shows all the information required byproject stakeholders, as defined in the communication management plan.
To prepare this report, you will need work performance information and work performance measurements.
Work Performance Information
工作绩效信息是项目状态的原始数据。它指的是工作的百分比已经完成,经过了多少时间,产生的成本等等。
It provides us with the current status of theproject。您可以使用此信息来创建工作绩效测量,然后创建工作绩效报告。
A few examples of work performance information are as follows:
- How much of the work has been completed?
- 是什么schedule’s progress?
- What cost has been incurred to date?
- What are the quality metrics of the product?
- 什么是风险状况?
- 是什么procurementperformance?
Work Performance Measurements
一旦获得状态,就可以将其与计划的进度进行比较,并提出工作绩效测量。它们是计划的进度与项目当前状态之间的比较。
Some examples of work performance measurements include:
Schedule Performance
Here you will compare the planned schedule with the actual schedule.
For example, for an activity that was scheduled to be completed in five days, work performance measurements show how long it actually took to complete.
成本性能
Here you will compare your planned expenditure with the actual expense.
例如,该活动的计划成本是多少,您实际花了多少才能完成?
质量Performance
Here you compare the planned performance with the actual performance.
For example, you will measure how many defects, tolerance, and threshold were allowed and how many occurred.
Risk Performance
在这里,您将看到您的有效性风险管理计划。
例如,您将看到发生了多少风险,与确定的风险,风险响应计划的有效性等等。
Procurement Performance
在这里你将比较卖方的实际性能nce against the planned performance.
The Difference Between Work Performance Information and Work Performance Measurements
The difference between work performance information and work performance measurements is as follows:
- Work performance information is the ‘as of now’ status of the deliverables, while work performance measurements are a comparison between the actual status and planned status.
- Work performance measurements are developed with the help of work performance information.
- 工作绩效信息的示例包括经过的时间和花费的钱,而成本差异和时间表差异,成本绩效指数和计划绩效指数以及更多是工作绩效衡量的示例。
Summary
Work performance information and work performance measurements help in赚取价值管理和预测。它们可以帮助您准备可以发送给利益相关者的绩效报告。基于此绩效报告,管理层决定如何进一步进行。
I hope you now have a better understanding of work performance information and work performance measurements.
Now you can move on to the next blog post, on theperformance report。
Hi Fahad,
Please update your explanation as you said you will be updating the blog, In the 5th version of the PMBOK Guide, Work Performance Measurement has been deleted and a new term Work Performance Date is added.
Your expert guidance is very helpful to me.
Already updated.
Here is the updated post:
//www.vhgallery.com/2013/10/work-performance-data-wpd-and-work-performance-information-wpi/
Hi Fahad,
感谢您的解释。But, in the PMBOK- Fifth edition, they have Work Performance data, Work Performance Information and Work Performance Reports……it doesn’t have Work Performance Measurements…..even the output of the “direct and manage project work” process is “work performance data” in 5th edition and “work performance information” in 4th edition…..i’m getting really confused….please help
您好Abhisek,我正要更新此博客以反映当前状态。
In the 5th version of the PMBOK Guide, Work Performance Measurement has been deleted and a new term Work Performance Date is added.
I am going to update this blog post very soon.
Here is the link for the updated blog post:
//www.vhgallery.com/2013/10/work-performance-data-wpd-and-work-performance-information-wpi/
Cleared the Confusion.
谢谢Fahad Bhai
You’re welcome Saurabh.
In the ‘In Brief” summary, should the first bullet point say WPM instead of WPI?
感谢您的文章!
为什么?有解释吗?
嗨,我很感谢您解释以下内容
问:作为绩效测量的一部分,以下哪项未完成?
1.Calculating Planned Value
2.估计的价值
3.计算等
4.Calculating Cost Variance
they say the correct answer is – Calculating Earned Value. Can you explain why is EV is not part of performance measurements?
谢谢!
Malika
我认为这是绩效报告的一部分。
Please refer the following post-
//www.vhgallery.com/2012/03/performance-report-in-project-management/
Let me know if you any other thoughts…
您会说WPM只是方差分析的结果吗?
方差分析是控制范围过程的工具和技术,工作绩效测量(WPM)是该过程的输出。
In short, answer to your question is – Yes.
Thanks a lot
Thank you; I really appreciate your explanations.
You are welcome Deidra.
dear
我想阐述您的帮助和关注
ali hussien
Thank you.
Have to disagree a bit here. Work performance data is the raw data. Work performance information is that data contextualized and put into a form that can be reported to stakeholders in a way they'll understand.
是的,你是对的,我同意你的看法。分歧在哪里?
WPI旨在收集项目的信息,WPM涉及分析信息。
Yes, you're right.