Schedule Variance (SV) and Cost Variance (CV) are two essential parameters in Earned Value Management. They help you analyze the project’s progress, i.e., how you are performing in terms of schedule and cost.
Assume you are managing a construction project. The client asks you to update them with the current status and progress of the project.
What do they mean by asking for these metrics?
How will you get this information?
客户要求提供有关迄今为止所产生的成本,完成工作以及项目在成本和时间表方面的表现的信息。
You will get this information with the help of Earned Value Management. Earned Value Management has three basic elements: Earned Value, Planned Value, and Actual Cost.
Earned Value is the value of the work completed to date. Planned Value is the money you should have spent as per the schedule. Actual Cost is the cost spent on the project to date.
这些基本元素可帮助您找到时间表差异和成本差异。时间表差异有助于了解您是否在计划中或计划中。成本差异有助于确定您是否不超过预算。
Variance analysis is the key to the success of any project, which is finished on time and within the approved budget. Variance analysis helps monitor your project performance, allowing you to takecorrective action一项要求,它可以让您知道您是否朝着正确的方向前进。
Schedule Variance (SV)
It is imperative for you to keep your project on schedule and Schedule Variance helps you complete it on time. It enables you to avoid unnecessary cost overruns due to a slip in schedule. Costs increase as you go over the stipulated time.
For example, you have rented some equipment for a specific duration of time and you may end up paying more if you need this equipment for longer. You may need to rent this equipment from other suppliers on an urgent, short-term contract at a higher price.
时间表差异是一种重要的分析工具,它可以让您知道您是按计划提前还是落后于计划。
The Formula for Schedule Variance (SV)
You can calculate Schedule Variance by subtracting Planned Value from Earned Value.
Schedule Variance = Earned Value – Planned Value
SV = EV – PV
From the above formula, we can conclude that:
- You are ahead of schedule if the Schedule Variance is positive.
- 你是落后于计划进度偏差如果我s negative.
- 如果时间表差异为零,则您将按计划进行。
When the project is complete, the Schedule Variance becomes zero because all Planned Value has been earned.
时间表差异的示例(SV)
You have a project to be completed in 12 months and the budget of the project is 100,000 USD. 6 months have passed and 60,000 USD has been spent, but on a closer review, you find that only 40% of the work has been completed.
Find the project’s Schedule Variance (SV) and determine if you are ahead of schedule or behind schedule.
Given in the question:
Actual Cost (AC) = 60,000 USD
Planned Value (PV) = 50% of 100,000
= 50,000 USD
请注意,在问题中,计划的价值不是具体给出的,但问题说一半的时间已经过去了。在这种情况下,您可以假设预算均匀分配,因此计划的价值将为50%。
Earned Value (EV) = 40% of 100,000
= 40,000美元
现在,
Schedule Variance = Earned Value – Planned Value
= 40,000 – 50,000
= -10,000 USD
The project’s Schedule Variance is -10,000 USD. You are behind schedule since it is negative.
Cost Variance (CV)
Cost Variance is as important as Schedule Variance. You must complete your project within the approved budget. Exceeding the planned budget is bad for you and your stakeholders.
一切都与金钱有关。客户对支出非常谨慎;因为与成本基线的任何偏差都会影响其利润。在最坏的情况下,他们可能必须在项目中投入更多的钱才能完成。如果合同是固定价格,这是有害的。
成本差异与该项目的成本基线有关。它为您提供有关您是否超过预算的信息,以美元计算。成本差异是对项目成本绩效的衡量标准。
The Formula for Cost Variance (CV)
Cost Variance can be calculated by subtracting the actual cost from the Earned Value.
成本差异=赚取价值 - 实际成本
CV = EV - AC
我们可以从上述公式中得出以下内容:
- You are under budget if the Cost Variance is positive.
- 如果成本差异为负,则您的预算超出了预算。
- You are on the budget if the Cost Variance is zero.
Example of Cost Variance (CV)
You have a project to be completed in 12 months, and the budget of the project is 100,000 USD. 6 months have passed, and 60,000 USD has been spent, but on closer review, you find that only 40% of the work has been completed so far.
Find the project’s Cost Variance (CV) and determine if you are under budget or over budget.
Given in the question:
Actual Cost (AC) = 60,000USD
Earned Value (EV) = 40% of 100,000 USD
= 40,000美元
现在,
成本差异=赚取价值 - 实际成本
CV = EV - AC
= 40,000 – 60,000
= –20,000 USD
Hence, the project’s Cost Variance is –20,000 USD, and you are over budget since it is negative
Cost Variance and Schedule Variance Comparision Table
Cost Variance and Schedule Variance Comparision Chart
Summary
Schedule Variance and Cost Variance are great tools for analyzing project health. As a project manager, you should monitor these variances for any deviations. If both variances are positive, this means that your project is progressing well. However, something is wrong if either variance is negative and you have to take corrective action to bring the project back on track.
您如何在项目中使用计划差异和成本差异?请在评论部分分享您的经验。
This blog post is the third in eleven series on Earned Value Management and project forecasting. Please read through my previous two posts before reading this post if you’re coming here from a search engine or a referral.
The following are the links for other blog posts:
- Earned Value Management
- Elements of Earned Value Management
- Budget at Completion in Project Management
- Cost Variance in Project Management
- Schedule Variance in Project Management
- Cost Performance Index in Project Management
- Schedule Performance Index in Project Management
- Schedule Variance and Cost Variance (You are here)
- Schedule Performance Index and Cost Performance Index
- Estimate at Completion
- Estimate to Complete
- To Complete Performance Index
Hi,
您知道在哪里可以在哪里找到此类问题?
Thanks
Hello Ahmad,
您可以尝试我的价值管理电子书。
//www.vhgallery.com/earned-value-management-for-the-pmp-certification-exam/
Hello Fahad,
谢谢您的PMP博客。这非常有帮助,易于理解。
在成本管理和《配方指南》中的EVM公式下浏览项目预算公式时,我与计划的价值,BAC,成本基线和项目预算相混淆。
项目预算=成本基线 +管理储备金
I understand that:
BAC =总计划价值(无管理储备)
Now Cost Baseline = Project Cost + Contingency Reserve
However, in the guide, I see the following statement:
“The project budget is also known as the Budget at Completion and denoted by BAC.”
So how is Project Budget the same as BAC as BAC does not include Management Reserve?
BAC =成本基线应该吗?
Appreciate your feedback.
thank you,
Mukund
Budget = BAC = Cost Baseline + Management Reserve
Hi Fahad ,
我认为,除非经过变更控制过程,否则管理储备将不会将其添加到成本基线之类的基线。
你好jajo,
管理储备不是成本基线的一部分,而是总预算(BAC)
SV must equal 0 upon completion regardless of the where the budget is.
What you are all missing is you can’t achieve 110%.
如果项目完成了所有任务,则项目完成。
法哈德是正确的。
Which aspect should we improve normally if a project is OVER BUDGET and BEHIND OF SCHEDULE?
请在此问题上分享一些观点。谢谢。
In this case you will need to find the exact cause of it. If there is problem with project plan or any unidentified risk has occurred caused you delay in schedule and cost.
根据问题,您将采取纠正措施。
Pretty useful. I have never seen previously scary arithmetic concepts made so simple. Indeed simply demystefied
Thanks. I doff my hat.
And come to think of it? Its free and I have paid a lot of money to learn these concepts at the Masters Level?
I’m glad Clem I could be of some help to you.
Hello Fahad,
Many thanks for the good work you are doing.
Please can you take a look at this question i found at one of your recommended links to the pool of pmp questions.
On your current project, EV = $45,000, AC = $50,000, PV = $40,000. What is the schedule variance as a percentage of the work accomplished at this point in time?
Suggested solution
the formula for schedule variance is SV = EV – PV. Therefore the schedule variance as a percentage of the work accomplished is PV/EV or +88.8%
Link to the question.
http://edwel.com/Free-Resources/PMP-Certification-Final-Exam.aspx
It is question number 2
Earned Value is 45,000 USD and Planned Value is 40,000 USD.
因此计划差异为1.125。
No idea why did they take inverse of it and come up with 88%.
我建议您可以与他们联系,如果您得到答复,请在此处更新。
谢谢法哈德
Can anyone explain me this scenario.
Planned Star Date = 1 March 2013
Planned End Date = 10 March 2013
Actual Start Date = 5 March 2013
Actual End Date = 15 March 2013
In both condition the time taken in 10 days only, but will this be considered in Schedule Variance as we have delayed the delivery? Kindly provide a concrete solution.
Based on these parameters, Schedule Variance can not be calculated.
为什么不?
I’m having the same dilemma…
In fact once the task is completed, this means all planned value has been earned; i.e. schedule variance will be zero.
I agree with Fahad there is no schedule variance in this case.
-Akhilesh