计划性能指数(SPI)成本绩效指数(CPI)

Schedule Performance Index (SPI) and Cost Performance Index (CPI) allow you to assess the project’s performance.

Schedule performance and cost performance are the two most important parameters of your project. SPI and CPI help you analyze the efficiency of any project.

Management is always looking at these parameters for any deviations from the baseline. Deviations from the baseline cost a great deal in project management. Therefore, it is important that you understand these concepts well.

由于这些概念涉及数学计算,因此许多有抱负的人忽略了它们。一旦您了解了数学,就可以轻松解决PMP考试的问题。

Schedule Performance Index (SPI)

The Schedule Performance Index (SPI) shows how you are progressing compared to the planned project schedule.

根据PMBOK指南,“计划绩效指数manbet最新版(SPI)是对计划效率的衡量标准,称为赚取价值与计划价值的比率。”

计划绩效指数为您提供有关项目时间效率的信息。

The Formula for the Schedule Performance Index (SPI)

You can find the Schedule Performance Index by dividing Earned Value by Planned Value.

Schedule Performance Index = (Earned Value) / (Planned Value)

SPI= EV / PV

You can conclude that:

如果SPI等于一项,完成的工作等于计划的工作;该项目按计划进行。

  • You have completed more work than planned if the SPI is greater than one; the project is ahead of schedule.
  • If you have completed less work than planned work if the SPI is less than one. The project is behind schedule.
  • 如果SPI等于一项,完成的工作等于计划的工作;该项目按计划进行。

确保在计算时间表绩效索引时考虑所有任务。有时,您只能考虑critical pathand ignore the rest, which will give you an incorrect result.

Therefore, make sure that non-critical activities are included.

Example of Schedule Performance Index (SPI)

You have a project to be completed in 12 months, and the budget is 100,000 USD. Six months have passed, and 60,000 USD has been spent, but upon closer review, you find that only 40% of the work has been completed so far.

Find the Schedule Performance Index and deduce whether the project is ahead or behind schedule.

Given in the question:

Actual Cost (AC) = 60,000USD

Planned Value (PV) = 50% of 100,000 USD

= 50,000美元

In the question, the Planned Value is not given. However, the project duration is 12 months and 6 months have passed. In this situation, you can assume the budget was distributed evenly for each month. Therefore, in 6 months, 50% of the budget will have been spent.

Earned Value (EV) = 40% of 100,000 USD

= 40,000美元

现在,

Schedule Performance Index (SPI) = EV / PV

= 40,000 / 50,000

= 0.8

Hence, the Schedule Performance Index is 0.8

You are behind schedule since the Schedule Performance Index is less than one.

Cost Performance Index (CPI)

The Cost Performance Index helps you to analyze the cost efficiency of the project. It measures the value of the work completed compared to the actual cost spent.

根据PMBOK指南,“成本绩效指数manbet最新版(CPI)是预算资源的成本效率的衡量标准,其表示为获得的价值与实际成本的比率。”新万博登录手机版

The Cost Performance Index specifies how much you are earning for each dollar spent on the project. It shows how well the project is sticking to the budget.

The Formula for the Cost Performance Index (CPI)

You can calculate the Cost Performance Index by dividing the earned value by the actual cost.

成本绩效指数=(赚取价值) /(实际成本)

CPI = EV / AC

You can conclude that:

  • You are earning more than what you have spent if the CPI is greater than one. The project is under budget.
  • You are earning less than what you have spent if the CPI is less than one. The project is over budget.
  • Earning and spending are equal if the CPI is equal to one. You can say that the project is proceeding as per the planned spending.

Example of Cost Performance Index (CPI)

You have a project to be completed in 12 months, and the budget of the project is 100,000 USD. 6 months have passed, and 60,000 USD has been spent, but upon closer review, you find that only 40% of the work has been completed.

Find the Cost Performance Index for this project and deduce whether you are under budget or over budget.

The following information is given in the question:

Actual Cost (AC) = 60,000USD

Planned Value (PV) = 50% of 100,000 USD

= 50,000 USD

Earned Value (EV) = 40% of 100,000 USD

= 40,000美元

现在,

Cost Performance Index (CPI) = EV / AC

= 40,000 / 60,000

= 0.67

Hence, the Cost Performance Index is 0.67

This means you are earning 0.67 USD for every 1 USD spent since the Cost Performance Index is less than one. This means you are over budget.

You have studied variance (SV and CV) and indexes (SPI and CPI). If you think that both sets of parameters provide the same information, you are wrong.

Both are required because there is a difference between variances and indexes; the former provides you with the difference between the two values and the latter gives a ratio.

The result comes in dollar form in cost or schedule variance. A negative variance means the project is in trouble. However, the project is in good shape if the variance is positive. The problem with variance is that you cannot compare the health of the project with another, even if your organization has many projects.

Therefore, you use the Performance Indexes to compare the health of a project among many projects. The Performance Index is the ratio between the parameters, and a glimpse of these ratios will help you determine the health of the project. This makes it easier for you to compare the relative health of projects. You can find efficiency through indexes.

成本绩效指标和进度dex Comparision Table

成本性能指数CPI和计划性能指数SPI比较表

成本绩效指标和进度dex Comparision Chart

schedule performance index and cost performance index chart

Summary

安排性能指数和成本绩效指数可帮助您分析项目的进度。这些措施可以帮助您确定是否符合标准。如果比率高于一个,您的状况很好。如果比率少于一个,则该项目存在问题,您应该接受corrective action. In ideal conditions, the ratio should be one.

This blog post is the fourth in a series of seven on Earned Value Management and project forecasting. Please read through my previous three posts before reading this post if you’re coming here from a search engine or a referral.

The following are the links for other blog posts: