Schedule Variance (SV) and Cost Variance (CV) are two essential parameters in Earned Value Management. They help you analyze the project’s progress, i.e., how you are performing in terms of schedule and cost.
Assume you are managing a construction project. The client asks you to update them with the current status and progress of the project.
索要这些指标是什么意思?
How will you get this information?
The client is asking for information on the cost incurred to date, work completed, and how the project is performing in terms of cost and schedule.
You will get this information with the help of Earned Value Management. Earned Value Management has three basic elements: Earned Value, Planned Value, and Actual Cost.
赚取的价值是迄今为止完成的工作的价值。计划的价值是您应该按时间表支出的钱。实际成本是迄今为止在项目上花费的费用。
These basic elements help you find Schedule Variance and Cost Variance. Schedule Variance helps to understand if you are behind or ahead of schedule. Cost Variance helps determine if you are under or over budget.
差异分析是任何项目成功的关键,该项目按时完成并在批准的预算之内完成。差异分析有助于监视您的项目绩效,使您可以接受corrective actionas soon as required, and it lets you know if you are going in the correct direction or not.
Schedule Variance (SV)
您必须按计划和计划差异将项目保持在准时完成。它使您能够避免由于时间表滑倒而避免不必要的成本超支。当您超过规定的时间时,成本增加。
For example, you have rented some equipment for a specific duration of time and you may end up paying more if you need this equipment for longer. You may need to rent this equipment from other suppliers on an urgent, short-term contract at a higher price.
Schedule Variance is a vital analytical tool, it lets you know if you are ahead of schedule or behind schedule in dollars.
The Formula for Schedule Variance (SV)
You can calculate Schedule Variance by subtracting Planned Value from Earned Value.
Schedule Variance = Earned Value – Planned Value
SV = EV - PV
从上面的公式,我们可以得出结论:
- You are ahead of schedule if the Schedule Variance is positive.
- You are behind schedule if the Schedule Variance is negative.
- You are on schedule if the Schedule Variance is zero.
When the project is complete, the Schedule Variance becomes zero because all Planned Value has been earned.
Example of Schedule Variance (SV)
You have a project to be completed in 12 months and the budget of the project is 100,000 USD. 6 months have passed and 60,000 USD has been spent, but on a closer review, you find that only 40% of the work has been completed.
查找项目的时间表差异(SV),并确定您是否提前或落后于计划。
在问题中给出:
Actual Cost (AC) = 60,000 USD
Planned Value (PV) = 50% of 100,000
= 50,000美元
Please note that in the question, the Planned Value is not specifically given but the question says that half of the time has passed. In such a situation, you can assume that the budget was evenly distributed, so the planned value will be 50%.
Earned Value (EV) = 40% of 100,000
= 40,000 USD
Now,
Schedule Variance = Earned Value – Planned Value
= 40,000 – 50,000
= -10,000 USD
The project’s Schedule Variance is -10,000 USD. You are behind schedule since it is negative.
Cost Variance (CV)
Cost Variance is as important as Schedule Variance. You must complete your project within the approved budget. Exceeding the planned budget is bad for you and your stakeholders.
Everything is about money. Clients are very cautious about spending; because any deviation from the cost baseline can affect their profit. In the worst case, they may have to put more money into the project to complete it. This is detrimental if the contract is fixed price.
Cost Variance deals with the cost baseline of the project. It provides you with information on whether you are over or under budget, in dollar terms. Cost Variance is a measure of the cost performance of a project.
The Formula for Cost Variance (CV)
Cost Variance can be calculated by subtracting the actual cost from the Earned Value.
Cost Variance = Earned Value – Actual Cost
CV = EV – AC
We can conclude the following from the above formula:
- 如果成本差异为正面,则您将处于预算状态。
- You are over budget if the Cost Variance is negative.
- You are on the budget if the Cost Variance is zero.
成本差异示例(CV)
You have a project to be completed in 12 months, and the budget of the project is 100,000 USD. 6 months have passed, and 60,000 USD has been spent, but on closer review, you find that only 40% of the work has been completed so far.
查找项目的成本差异(CV),并确定您是预算范围还是预算超出预算。
在问题中给出:
实际成本(AC)= 60,000USD
Earned Value (EV) = 40% of 100,000 USD
= 40,000 USD
Now,
Cost Variance = Earned Value – Actual Cost
CV = EV – AC
= 40,000 - 60,000
= –20,000 USD
Hence, the project’s Cost Variance is –20,000 USD, and you are over budget since it is negative
成本差异和时间表差异比较表
Cost Variance and Schedule Variance Comparision Chart
Summary
Schedule Variance and Cost Variance are great tools for analyzing project health. As a project manager, you should monitor these variances for any deviations. If both variances are positive, this means that your project is progressing well. However, something is wrong if either variance is negative and you have to take corrective action to bring the project back on track.
How are you using Schedule Variance and Cost Variance in your project? Please share your experience in the comments section.
这篇博客文章是关于赚取价值管理和项目预测的11个系列中的第三篇。如果您是从搜索引擎或转介来到这里,请在阅读本文之前阅读之前的两篇文章。
The following are the links for other blog posts:
你好,
Do you know where can I find more questions like this online?
Thanks
Hello Ahmad,
You can try my Earned Value Management eBook.
//www.vhgallery.com/earned-value-management-for-the-pmp-certification-exam/
Hello Fahad,
Thank you for the PMP blog. This has been very helpful and is easy to understand.
While going through the Project Budget formula under Cost Management and the EVM formulae from the Formula guide I got confused with the Planned Value, BAC, Cost Baseline and Project Budget.
Project Budget = Cost Baseline + Management Reserve
I understand that:
BAC = Total Planned Value (without Management Reserve)
现在成本基线=项目成本 +应急储备
However, in the guide, I see the following statement:
“项目预算也称为完成时的预算,并由BAC表示。”
怎么是项目预算和BAC BAC一样一样es not include Management Reserve?
Should BAC = Cost Baseline?
感谢您的反馈。
thank you,
Mukund
Budget = BAC = Cost Baseline + Management Reserve
Hi Fahad ,
I think management reserve will not be added to the cost baseline like contingency reserve unless it goes through change control process.
Hello Jajo,
Management reserve is not part of the cost baseline but included in the total budget (BAC)
SV must equal 0 upon completion regardless of the where the budget is.
你们都缺少的是您无法取得110%的成绩。
If the project has completed all tasks, the project is complete.
Fahad is correct.
Which aspect should we improve normally if a project is OVER BUDGET and BEHIND OF SCHEDULE?
Kindly share some viewpoints on this matter. Thank you.
In this case you will need to find the exact cause of it. If there is problem with project plan or any unidentified risk has occurred caused you delay in schedule and cost.
基于这个问题,您将采取纠正行动n.
非常有用。我从未见过以前令人恐惧的算术概念变得如此简单。的确,简单地脱颖而出
谢谢。我戴上帽子。
And come to think of it? Its free and I have paid a lot of money to learn these concepts at the Masters Level?
I’m glad Clem I could be of some help to you.
Hello Fahad,
非常感谢您所做的良好工作。
Please can you take a look at this question i found at one of your recommended links to the pool of pmp questions.
On your current project, EV = $45,000, AC = $50,000, PV = $40,000. What is the schedule variance as a percentage of the work accomplished at this point in time?
Suggested solution
附表方差的公式为SV = EV - PV。因此,完成工作的时间表差异是PV/EV或 +88.8%
Link to the question.
http://edwel.com/Free-Resources/PMP-Certification-Final-Exam.aspx
It is question number 2
赚取的价值为45,000美元,计划价值为40,000美元。
So the schedule variance will be 1.125.
No idea why did they take inverse of it and come up with 88%.
I suggest you can contact them and if you get a reply, please update here as well.
Thanks Fahad
谁能向我解释这种情况。
Planned Star Date = 1 March 2013
Planned End Date = 10 March 2013
Actual Start Date = 5 March 2013
Actual End Date = 15 March 2013
在这两种情况下,仅在10天内花费的时间,但是随着我们推迟交付的时间,这是否会在计划差异中考虑?请提供混凝土解决方案。
Based on these parameters, Schedule Variance can not be calculated.
Why Not?
我有同样的困境...
事实上,一旦任务完成,这意味着所有planned value has been earned; i.e. schedule variance will be zero.
I agree with Fahad there is no schedule variance in this case.
-Akhilesh